Domino Sugar Refinery.
260 ft, inside and out.

Facade repairs with two 250 ft lifts working in tandem, and maintenance of the 260 ft chimney from our 300 ft lift, including inside its opening. Finished on time.

260 ft chimneyA-300 300 ft lift106 ft side reach2 250 ft lifts on the facade12 ft basket with work lightsRiverfront strong winds260 ft chimneyA-300 300 ft lift106 ft side reach2 250 ft lifts on the facade12 ft basket with work lightsRiverfront strong winds260 ft chimneyA-300 300 ft lift106 ft side reach2 250 ft lifts on the facade12 ft basket with work lightsRiverfront strong winds260 ft chimneyA-300 300 ft lift106 ft side reach2 250 ft lifts on the facade12 ft basket with work lightsRiverfront strong winds

How the job went.

  1. The job

    Facade repairs and maintenance of the 260 ft chimney at the historic Domino Sugar Refinery, where a modern glass office building sits inside the 19th-century structure.

  2. The problem

    Pipe scaffolding was too costly, and suspended scaffolding would not work with the way the brick facade is tied to the building inside. Strong riverfront winds ruled out a crane basket at the chimney.

  3. What we sent

    Two 250 ft lifts on the facade, working in tandem, with work lights in the 12 ft baskets for late evenings. For the chimney, our A-300 with 106 ft of side reach.

  4. How it went

    Technicians worked on every side of the chimney and inside its opening, and installed a net to keep out birds and snow. The A-300 stayed steady in the wind.

The lift on this job.

Alpha A-300 truck-mounted boom liftA-300Drag to turn. 3D model: A-165, shown for illustration.
300ftWorking heightSee the A-300 page.
137 ftSide reach
12 ftExtra-large basket
1,322 lbCrew, tools, materials
54'9"Upper boom extension
15'6"Minimum outrigger spread
220° each wayBasket rotation
Up and overUnder, up, over and back
Spec sheet (PDF)Every figure for the A-300 on one page.

The result, in numbers.

Photos from the site.

Aerial view of the Domino Sugar Refinery with an Alpha boom at the chimney
Two Alpha baskets at the brick facade below the Domino Sugar sign
Top-down view of the Alpha boom reaching the chimney from the street
Two Alpha booms working the refinery facade side by side
The Alpha basket lowered inside the chimney opening, seen from above
Two workers in the Alpha basket on the chimney top, the Williamsburg Bridge behind
The refinery on the riverfront with the Alpha booms at the facade
Two Alpha baskets at the chimney and the facade under the glass roof
The Alpha boom running up the side of the 260 ft chimney
Two Alpha baskets at the chimney and the facade under the glass roofGet the full case study. Open the PDF.Two pages: the challenge, the solution and the outcome, with photos. Open PDF

More jobs like this one.

All 36 projects →

Book your lift. We handle the rest.

01Tell us the jobAddress, height, what you need to reach.
02We call you backThe right lift, the permits and a price.
03The lift arrivesOperator on site, basket up within 15 minutes.

Get a quote